Darracott Windfarm Infrastructure

Client:
FIM Services Ltd
Contract Value:
£543k
Contract Date:
2010 – 2011
Location:
Darracott

Design and construct balance of plant civils and electrical infrastructure for three Gamesa 850KW turbines.

The site is located in farmland near the town of Torrington, Devon, and is situated above a water supply reservoir. Strict environmental controls were required to ensure containment of silt run-off from site construction operations, which proved successful –  despite the majority of the construction works being carried out over the wet winter period.

Works included:

  • Design and construction of site access tracks and extension of existing culvert
  • Design and construction of three concrete turbine foundations and three crane pads
  • Substation
  • CDM supervision of turbine erection commissioning
  • Diversion of WPD overhead lines and equipment to enable wind farm development

Also in this section

Jones Bros is one of the UK’s leading civil engineering contractors with a wealth of experience across a broad range of sectors.
© 2026 Jones Bros. All rights reserved.
There are many variations of passages of Lorem Ipsum available, but the majority have suffered alteration in some form.

Let’s Work Together